Skip to content
Construction Metric

Glossary

The language of the record

Plain-English definitions of the terms that decide construction projects and disputes, written by people who have used them in anger.

Adjudication

Adjudication is the fast statutory dispute process available on UK construction contracts: a party refers a dispute to a

As-built records

As-built records document what was actually constructed, as distinct from what was designed: final routes of services, a

Building Safety Act 2022

The Building Safety Act 2022 is the law passed after the Grenfell Tower fire to overhaul how building safety is managed

Building safety gateways

The gateways are the three control points the Building Safety Act places across a higher-risk building project. Gateway

CDE (common data environment)

A common data environment is the agreed single source of truth for project information: the platform and processes throu

CDM 2015

The Construction (Design and Management) Regulations 2015 are the UK regulations governing how construction projects are

Contemporaneous records

Contemporaneous records are documents created at or close to the time of the events they describe: site diaries, photogr

Critical path

The critical path is the longest chain of dependent activities through a programme: the sequence with no float, where an

Daywork

Daywork is a method of valuing work on the basis of the labour, plant and materials actually used, plus agreed percentag

Dutyholder

Dutyholder is the umbrella term for the parties who carry legal duties on a construction project: the client, designers,

EOT (extension of time)

An extension of time moves the contractual completion date because of delay caused by events the contract allocates to t

Golden thread

The golden thread is the Building Safety Act’s requirement for an accurate, up-to-date and accessible record of building

Higher-risk building

A higher-risk building is one that falls within the stricter part of the Building Safety Act regime. During design and c

ISO 19650

ISO 19650 is the international standard for managing information over the whole life cycle of a built asset. It grew out

ITP (inspection and test plan)

An inspection and test plan sets out the quality verification for a scope of work: what will be inspected or tested, at

Liquidated damages (LDs)

Liquidated damages are the pre-agreed sum the contractor pays for late completion, usually expressed per week or per day

Loss and expense

Loss and expense is the money side of employer-caused delay and disruption: the contractor’s entitlement to be reimburse

Mandatory occurrence reporting

Mandatory occurrence reporting is the Building Safety Act duty to report certain safety occurrences on higher-risk build

Method statement

A method statement describes how a specific piece of work will be carried out: the sequence of operations, the plant and

NCR (non-conformance report)

A non-conformance report records work, materials or processes that do not meet the specified requirement: the wrong conc

Pay less notice

Under the UK Construction Act payment regime, a paying party that intends to pay less than the sum notified must issue a

Practical completion

Practical completion is the contractual milestone at which the works are complete enough for the employer to take and us

Preliminaries (prelims)

Preliminaries are the costs of running the project as a whole rather than any measured work item: site management and su

Principal contractor

The principal contractor is the contractor appointed to control the construction phase where more than one contractor is

Principal designer

The principal designer is the designer appointed to control the design phase where more than one contractor is involved.

RAMS

RAMS stands for Risk Assessment and Method Statement, the paired documents that describe how a construction task will be

Retention

Retention is a percentage of each payment (commonly three to five per cent) withheld by the paying party as security for

RFI (request for information)

A request for information is the formal question a contractor raises when the design information is missing, ambiguous o

Site diary

A site diary is the daily record of what actually happened on a construction site: weather, labour and plant on site, wo

Snagging

Snagging is the process of identifying and recording minor defects and unfinished items, typically as a project approach

Toolbox talk

A toolbox talk is a short, focused briefing delivered to the workforce on site, usually on a specific hazard or task: wo

Variation

A variation is a change to the works from what the contract described: more work, less work, different work, or changed